Skip to main content.

Children’s Play Area Improvement Programme Consultation 07

Contact

Communications and Consultation Team

Tel: 01509 634989

Related Documents

Children’s Play Area Improvement Programme 2007

Contact

Communications and Consultation Team

Tel: 01509 634989

Email: consultation@charnwood.gov.uk

Play Rangers

Tel: Matthew Forsyth (01509) 634836

Email: matthew.forsyth@charnwood.gov.uk

Children’s Play Area Improvement Programme 2007

Phase 3 of the Improvement Programme at Jubilee Park, Cumberland Road Playing Field and Rendell Street was successfully completed by Christmas 2007 at a cost of £366,000.

The chosen company was Proludic who are based at West Bridgford, Nottingham. The designs are as follows:Jubilee Park

Jubilee Park Design

Cumberland Road

Cumberland Road

Rendell Street

Rendell Street Design

Orders have been placed and construction timetable is as follows:

Jubilee Park
Start date – 22nd October
Completion – 21st December

Jubilee Park Design

Cumberland Road
Start date – 29th October
Completion – 27th November

Cumberland Road

Rendell Street
Start date – 26th November
Completion – 14th December

Rendell Street Design

The 3 final selections have been developed into full design layouts by the council’s partner, Bellinger Design.

Last updated: Fri 22nd January, 2010 @ 10:10