Phase 3 of the Improvement Programme at Jubilee Park, Cumberland Road Playing Field and Rendell Street was successfully completed by Christmas 2007 at a cost of £366,000.
The chosen company was Proludic who are based at West Bridgford, Nottingham. The designs are as follows:Jubilee Park
Cumberland Road
Rendell Street
Orders have been placed and construction timetable is as follows:
Jubilee Park
Start date – 22nd October
Completion – 21st December
Cumberland Road
Start date – 29th October
Completion – 27th November
Rendell Street
Start date – 26th November
Completion – 14th December