Question

S106 Funding p/00/2507/2 Hallam Fields
The information shown on your website is somewhat vague as it only show amounts due and amounts received and ignores amounts outstanding and amounts actually spent. So could you please supply the following information.

As at 1 August 2013 how many houses have been completed on Hallam Fields and based on the criteria contained in the agreement how much S106 funding should have been paid on the based on that number of houses.

How much money has actually been paid and what for

how much of the money paid has actually been spent and what on.

Answer

As at 1 August 2013 how many houses have been completed on Hallam Fields and based on the criteria contained in the agreement how much S106 funding should have been paid on the based on that number of houses.
The developer is obliged under the 106 agreement to report to us each year the number of occupations as at 16th June. They are not obliged to provide that information at any other date in the year, nor are they obliged to report on completions of builds.

As at 16th June 2013 there were approximately 500 occupations of the site in question.

I have attached the S106 agreement which sets out what monies will be paid at what stage of the development.

How much money has actually been paid and what for and how much of the money paid has actually been spent and what on.
Please see below:

P/00/2507/2 Hallam Fields   
Purpose  Amount Received   Spent   Details on spend  Balance held
 All Weather Pitch Contribution      50,000.00       50,000.00
Great Central Railway Contribution      31,746.03        31,746.03  Paid to David Clarke Railway Trust and used to improve the station at Leicester North                    -  
Public Art Contribution      57,142.86        57,142.86  Paid to Leicestershire County Council in order to deliver a scheme of public art on the park and ride site at Birstall which is being provided as part of the Hallamfields mixed use development                   -  
Environmental/Traffic Management Contribution    131,666.67        26,845.00  Paid to Birstall Parish Council and used as a contribution towards the Sibson Road car park and associated environmental improvements                    -  
Environmental/Traffic Management Contribution      104,821.67  Paid to Leicestershire County Council in order to undertake environmental improvements at Wanlip Lane/Stonehill Avenue, Birstall 
    270,555.56      220,555.56      50,000.00